Nador Port project in Morocco is nearing completion, with 93% of the work already finished. The remaining works are planned to be completed soon.
Final Acceptance Letter Has Been Received For Safi Port Project
Final acceptance letter has been received on 20.11.2020 for “Safi Port” Project, which was undertaken as STFA Deniz İnşaat A.Ş. by the contract signed on 07.03.2013 with the Ministry of Equipment and Transport.
The project consists of construction work for the New Port of Safi: Protection Structures, Coal Dock, Service Dock, Dredging and General Backfills; Main Breakwater and Lee Breakwater (approx. 3000 m), Coal Berth Quay Wall, Service Quay Wall.
First Ship Is Docked At Safi Port Project
The first ship has been docked at Safi Port after the completion of our Morocco New Safi Port Project.
First Caisson Has Been Successfully Submerged In Nador Port Project
In Nador Port Project, which is constructed in Morocco; the first caisson has been successfully submerged. Following the installation of the superstructure (steel grids and generators) and pumps to the C3A caisson (dimensions 21,30 m x 28,30 m x 25,70 m) with a weight of 8.300 tons, it was transported to the Barge by using 50 Nos of hydraulic jacks each 250 t capacity.
3.150 m3 concrete and 702 t rebar were used in the said caisson.
We would like to congratulate our colleagues for this great achievement and wish them continuous success.
STFA’s first Project in Morocco
New Safi Port Project, the first in Morocco, was undertaken.